Step 1: Update Project Libre with Resource InputsThe following steps should be followed when adding resource input in Project Libre.Set the resource input
Open Project Libre
Open your project .
Select Resources (Top tool bar)
Add your resources
Enter Resource Name
Enter Resource Type
Enter Rates
Enter Base Calendar
Enter the remaining resources using the same format as above.
Set your resource information
Select Resource
Select information
Enter Cost, Resource availability or additional information
Go back to task to add your resources
Go to task
Click on Gantt
Select the task
Select assign resourceAssign resources and unit percentages
Add remaining resources
Make sure to save your information
Step 2: Update Project Libre with Cost InputsThe following steps should be followed when setting up your Course Project with Project Libre.Set the cost input
Select a column
Insert a column by right clicking
Select cost
Click ok
Cost should be displayed from resource input
Insert new columnSelect total slack
Your total slack should be displayed
Insert new columnSelect Free slack
Your free slack should be displayed
Select FileClick Save Baseline
Select Baseline one
Select Entire project
Click ok
Go print preview
Adjust your scale
Or Fit to one page
Select Printer setting to PDF
Or save image in word and crop
Submit in the dropbox